EPB-2012-0150 INTERSTATE POWER AND LIGHT COMPANY On April 2, 2012, IPL filed an updated Emissions Plan and Budget (EPB) pursuant to Iowa Code § 476.6(21). IPL’s EPB update addresses its multi-year plan and budget for managing regulated emissions from its Iowa generating facilities that are fueled by coal. IPL’s updated EPB details its capital, operations and maintenance, and emissions allowance costs for 2013 and 2014, as well as provides information on projected capital costs through 2017. On October 2, 2012, the Board issued an order requiring IPL to file additional information. IPL filed the information on October 17, 2012. On November 5, 2012, IPL filed an amendment to its updated EPB. Also on that date, IPL and the Office of Consumer Advocate filed a partial settlement and motion to approve the settlement. The docket is pending.